Sample Project
84 new rental units · $37,500,000 total development cost · Draw 7 at 39% complete
OverviewDeal mapFlow of FundsPay app checkChecklist and QADuplication of benefitsAgency viewSample files
What the grantee's reviewer sees
A read-only view of the released draw files, the payment timing for each draw, and a way to send requests to the developer. Drafts, QA notes and compliance marks are never shown.
| Project status | Compliance checks | ||||||
|---|---|---|---|---|---|---|---|
| Draw | Received | Approved | Paid | Days from receipt | Days from approval | 30 days from receipt 2 CFR 200.305(b)(3) | 30 days from approval Sample agreement |
| 6 | May 4, 2026 | May 22, 2026 | June 12, 2026 | 39 | 21 | Past 30 days by 9 | Met |
| 7 | July 8, 2026 | Not confirmed | Not paid | 37* | - | Past 30 days by 7 and counting | Approval date needed |
What RAP does
When a draw runs past the payment terms, RAP drafts a status letter for the developer to sign, citing the agreement and 2 CFR 200.305: it asks for the approval date, the expected payment date and payment of any undisputed amount, with written notice of anything held. Read the sample letter.