84 new rental units · $37,500,000 total development cost · Draw 7 at 39% complete
OverviewDeal mapFlow of FundsPay app checkChecklist and QADuplication of benefitsAgency viewSample files
One budget, many layers
Every source pays a share of the same $37,500,000 budget. The construction loan pays costs first and is repaid; it is not an extra source on top of the permanent ones.
LIHTC equity $16,800,000CDBG-DR loan $14,250,000Permanent mortgage $4,100,000Deferred developer fee $1,250,000Trust fund grant $750,000Insurance proceeds $350,000
Construction to permanent
The construction loan is the bridge. Each draw is split between CDBG-DR and the construction loan; equity installments and the permanent mortgage complete the permanent sources and repay the bridge.
| # | Date | Source | Event | Basis |
|---|---|---|---|---|
| 1 | Nov 14, 2025 | LIHTC equity | Installment 1 $2,520,000 at closing | Sample partnership agreement |
| 2 | Nov 14, 2025 | Project | Closing | Sample data |
| 3 | Jul 8, 2026 | CDBG-DR | Draw 7 received by the grantee | Sample data |
| 4 | Nov 15, 2026 | LIHTC equity | Installment 2 $5,040,000 at 50% completion | Sample partnership agreement |
| 5 | Sep 30, 2027 | LIHTC equity | Installment 3 $6,720,000 at completion | Sample partnership agreement |
| 6 | Jan 31, 2028 | Bank | Conversion: permanent mortgage $4,100,000 funds and the construction loan is repaid | Sample loan agreement |
| 7 | Jun 30, 2028 | LIHTC equity | Installment 4 $2,520,000 at Form 8609 | Sample partnership agreement |
Permanent sources
| Source | Provider | Amount |
|---|---|---|
| CDBG-DR loan | State CDBG-DR Grantee (sample) | $14,250,000 |
| LIHTC equity | Sample Tax Credit Investor | $16,800,000 |
| Permanent first mortgage | Sample Community Bank | $4,100,000 |
| Local housing trust fund grant | Sample City Housing Trust Fund | $750,000 |
| Insurance proceeds | Owner (prior storm-damaged building) | $350,000 |
| Deferred developer fee | Sample Housing Partners LLC (Developer) | $1,250,000 |
| Total | $37,500,000 |
Uses
| Line | Amount |
|---|---|
| Acquisition | $1,200,000 |
| Construction contract (incl. sitework $2,100,000) | $26,400,000 |
| Hard cost contingency (5%) | $1,320,000 |
| Architecture and engineering | $1,450,000 |
| Permits and fees | $380,000 |
| Legal | $420,000 |
| Builder's risk and liability insurance | $360,000 |
| Construction interest | $1,120,000 |
| Financing fees | $450,000 |
| Developer fee | $3,400,000 |
| Reserves | $1,000,000 |
| Total development cost | $37,500,000 |
Funding sequence
- Closing: equity installment 1 ($2,520,000) and the trust fund grant pay acquisition and early soft costs.
- Construction: each hard-cost draw is split 50% CDBG-DR and 50% construction loan, net of 10% retainage. CDBG-DR also funds 50% of contingency and $390,000 of architecture and engineering.
- Interest and soft costs: construction interest from the construction loan; other soft costs from equity.
- Completion and conversion: equity installments 3 and 4 and the permanent mortgage repay the construction loan; the deferred fee is paid from cash flow.
| LIHTC equity installment | Amount |
|---|---|
| 1. At closing (15%) | $2,520,000 |
| 2. At 50% construction completion (30%) | $5,040,000 |
| 3. At construction completion (40%) | $6,720,000 |
| 4. At IRS Form 8609 issuance (15%) | $2,520,000 |
What RAP does
RAP reads the executed loan, grant and partnership agreements and writes this sequence down once, so the developer, lender, investor and agency all work from the same picture. The portal then applies it to every draw.