84 new rental units · $37,500,000 total development cost · Draw 7 at 39% complete
OverviewDeal mapFlow of FundsPay app checkChecklist and QADuplication of benefitsAgency viewSample files
Draw 7 compliance checklist: Not ready
| Item | Status |
|---|---|
| AIA G702/G703 pay application | Footing error |
| Contractor's sworn statement | Met |
| Conditional lien waivers (this period) | Missing: Electrical |
| Unconditional lien waivers (prior period) | Met |
| Davis-Bacon certified payrolls (WH-347) | Missing: one week |
| Section 3 quarterly report | Met |
| Inspecting architect's report | Met |
| Title date-down endorsement | Pending review |
| Change order log | Missing: Change Order 3 |
| Insurance certificates current | Met |
| QA review (second RAP reviewer) | Not started |
What RAP does
RAP builds the checklist from each source's requirements, tells the developer exactly what to get and from whom, confirms signatures, and assigns a separate QA reviewer to every project. The result is one complete submission instead of rounds of deficiency notices.