Sample Project
84 new rental units · $37,500,000 total development cost · Draw 7 at 39% complete
Draw status: Not ready
| Check | Result |
|---|
| Footing test | Fails. The G703 this-period column totals $1,842,600.01; the G702 states $1,842,600.00. One cent on the Plumbing line. |
| Budget limit | Over. Roofing completed to date $652,000 against a $640,000 scheduled value (101.9%) with no approved change order. |
| Required documents | Missing: electrical subcontractor's conditional lien waiver; one week of Davis-Bacon certified payroll. |
| Signature gate | Unsigned: contractor's certification on the G702. |
Continuation sheet (G703), Pay Application 7
| No. | Description | Scheduled value | Previous | This period | To date | % |
|---|
| 01 | General conditions | $1,980,000 | $640,000 | $140,000 | $780,000 | 39.4% |
| 02 | Sitework | $2,100,000 | $1,700,000 | $120,000 | $1,820,000 | 86.7% |
| 03 | Concrete | $2,950,000 | $2,100,000 | $180,000 | $2,280,000 | 77.3% |
| 04 | Masonry | $1,240,000 | $250,000 | $125,000 | $375,000 | 30.2% |
| 05 | Framing and carpentry | $4,380,000 | $1,540,000 | $440,000 | $1,980,000 | 45.2% |
| 06 | Roofing | $640,000 | $420,000 | $232,000 | $652,000 | 101.9% |
| 07 | Windows and doors | $1,450,000 | $0 | $145,000 | $145,000 | 10.0% |
| 08 | Plumbing | $2,860,000 | $620,000 | $214,300.01 | $834,300 | 29.2% |
| 09 | HVAC | $2,510,000 | $480,000 | $106,300 | $586,300 | 23.4% |
| 10 | Electrical | $2,430,000 | $520,000 | $140,000 | $660,000 | 27.2% |
| 11 | Finishes | $2,640,000 | $0 | $0 | $0 | 0.0% |
| 12 | Elevators | $820,000 | $0 | $0 | $0 | 0.0% |
| 13 | Contractor fee and overhead | $400,000 | $180,000 | $0 | $180,000 | 45.0% |
| Total | $26,400,000 | $8,450,000 | $1,842,600.01 | $10,292,600.01 | 39.0% |
Draw 7 amount
| Item | Amount |
|---|
| Completed this period (G702) | $1,842,600 |
| Retainage (10%) | ($184,260) |
| Net hard cost | $1,658,340 |
| Construction interest | $68,400 |
| Architecture and engineering | $42,500 |
| Draw 7 total | $1,769,240 |
Draw 7 by source
| Source | Amount | Basis |
|---|
| CDBG-DR | $829,170 | 50% of net hard cost |
| Construction loan | $897,570 | 50% of net hard cost plus interest |
| LIHTC equity | $42,500 | Architecture and engineering |
| Total | $1,769,240 | |
What RAP does
The portal finds the problems; RAP decides what fixes them. Here, the roofing overrun cannot be paid by raising the line. RAP's review note asks for Change Order 3 from contingency and lender consent, and confirms the contingency balance supports it. Read the sample RAP review note.
Sample demonstration by Rock Advisory Partners, LLC. Federal rules cited are public law; the sample agreements and parties are fictional.